Procedure of Issuing Building
Permit & Building Completion Certificate from DM
Through the Unified Dubai BPS Window
1 First Step:
Submission
Applications are submitted through
Responsibility:
Request To Obtain
Dubai BPS where applicants have to
Building Permit
attach all required drawings, documents,
fill building card information, and pay
permit fees. Then, applications are
received by participated Governmental
Authorities through unified Dubai BPS
window. The required NOCs and the
Consultant
Building Permit will be issued and all
Steel Structural
drawings will be stamped. Contractor or
Design and Build Contractor
Consultant can download them from the
(for G + 1 industrial steel buildings)
system.
2 Second Step:
Submission
Request for Structural
Responsibility:
All Structural Inspection applications are
Inspection on:
received through the system and the
1-Shoring Works & Foundations.
elements will be inspected. Inspection on
2- Cast concrete slabs
foundations will be conducted through a
Unified Inspection Committee which
includes DM concerned departments :
Building Control Department and Survey
Contractor
Department.
Third Step:
Submission
All Completion & Services Connection
3
Responsibility:
applications are received through the
system. Inspections on new buildings and
steel structurs (if any) will be conducted
Request for Final Inspection
through Unified Inspection Committee
for Completion & Services
between all concerned government
Connection
authorities
(Building
Control
Department, Survey Department, Dubai
Civil Defense, RTA, Etisalat and Du)
Contractor
according to the project type. All services
will be connected and a Certificate of
Completion will be issued immediately.